[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140441":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1140441,799,1,"单选题","下列组织工具中，可以用来对项目的结构进行逐层分解，以反映组成该项目的所有工作任务的是（ ）。 2016",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目结构图",true,{"key":16,"text":17,"correct":18},"B","组织结构图",false,{"key":20,"text":21,"correct":18},"C","工作任务分工表",{"key":23,"text":24,"correct":18},"D","管理分工表","本题考查的是项目结构图。项目结构图通过树状图的方式对一个项目的结构进行逐层分解，以反映组成该项目的所有工作任务。参见教材8。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]