[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140418":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1140418,799,2,"多选题","关于建设工程项目管理的说法，正确的有（ ）。 2016",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","业主方是建设工程项目生产过程的总组织者",true,{"key":16,"text":17,"correct":14},"B","建设工程项目各参与方的工作性质和工作任务不尽相同",{"key":19,"text":20,"correct":21},"C","建设工程项目管理的核心任务是项目的费用控制",false,{"key":23,"text":24,"correct":21},"D","施工方的项目管理是项目管理的核心",{"key":26,"text":27,"correct":14},"E","实施建设工程项目管理需要有明确的投资、进度和质量目标","ABE","本题考查的是建设工程项目管理的目标和任务。项目管理的核心任务是项目的目标控制。业主方是建设工程项目生产过程的总组织者，对于一个建设工程项目而言，业主方的项目管理往往是该项目的项目管理的核心。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]