[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140413":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1140413,799,2,"多选题","建设工程项目的实施阶段包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","设计阶段",true,{"key":16,"text":17,"correct":14},"B","设计准备阶段",{"key":19,"text":20,"correct":21},"C","可行性研究阶段",false,{"key":23,"text":24,"correct":14},"D","施工阶段",{"key":26,"text":27,"correct":14},"E","动用前准备阶段","ABDE","本题主要考查建设工程项目管理的目标和任务。 项目实施阶段包括：设计前准备阶段、设计阶段、施工阶段、动用前准备阶段、保修阶段。 综上所述，本题正确答案为ABDE。@##",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]