[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140408":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1140408,799,1,"单选题","项目实施阶段包括一系列的工作，以下属于其工作内容的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计变更",true,{"key":16,"text":17,"correct":18},"B","确定项目定义",false,{"key":20,"text":21,"correct":18},"C","编写可行性研究报告",{"key":23,"text":24,"correct":18},"D","项目决策风险分析","本题主要考查建设工程项目实施阶段工作。 A项：设计变更属于项目实施阶段工作，所以A项正确。 BCD项：确定项目定义、编写可行性研究报告、项目决策风险分析均属于决策阶段工作。所以BCD项错误。 综上所述，本题正确选项是A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]