[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140405":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1140405,799,1,"单选题","编制可行性研究报告属于建设工程项目（ ）阶段的主要任务。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","决策",true,{"key":16,"text":17,"correct":18},"B","设计",false,{"key":20,"text":21,"correct":18},"C","动工前准备",{"key":23,"text":24,"correct":18},"D","施工","本题主要考查建设工程项目管理的内涵、目标和任务。 项目决策阶段项目管理的主要工作是编制项目建议书和可行性研究报告。 本题正确选项为A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]