[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140404":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1140404,799,1,"单选题","建设工程项目管理的核心任务是项目的目标（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","比较",false,{"key":16,"text":17,"correct":14},"B","管理",{"key":19,"text":20,"correct":21},"C","控制",true,{"key":23,"text":24,"correct":14},"D","规划","本题主要考查项目管理的任务。 项目管理的核心任务是项目的目标控制，因此按项目管理学的基本理论，没有明确目标的建设工程不是项目管理的对象。 综上所述，本题正确选项是C项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]