[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140401":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1140401,799,1,"单选题","建设工程项目管理的核心任务是项目的（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","目标规划",false,{"key":16,"text":17,"correct":14},"B","目标比选",{"key":19,"text":20,"correct":14},"C","目标论证",{"key":22,"text":23,"correct":24},"D","目标控制",true,"本题主要考查建设工程项目管理的核心任务。 建设工程项目管理的核心任务是项目的目标控制，包括：费用控制、进度控制和质量控制。 综上所述，本题正确答案为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]