[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140393":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1140393,799,1,"单选题","建设工程项目实施阶段管理工作的主要任务是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确定项目实施的组织",false,{"key":16,"text":17,"correct":18},"B","通过管理使项目的目标得以实现",true,{"key":20,"text":21,"correct":14},"C","确定建设项目的进度目标",{"key":23,"text":24,"correct":14},"D","通过管理保证建设项目的质量","本题主要考查建设工程项目管理的目标和任务。 项目的实施阶段包括设计前的准备阶段，设计阶段，施工阶段，动用前的准备阶段和保修期。项目实施阶段的主要任务是通过管理使项目目标得以实现。 综上所述，本题正确答案为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]