[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140387":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1140387,799,2,"多选题","根据《建设工程施工合同(示范文本)》(GF—2013一0201)，除在专用合同条款中明确的事项外，承包人必须向发包人提交（ ），项目经理才能履行职责。 2016",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目经理与承包人之间的劳动合同",true,{"key":16,"text":17,"correct":18},"B","项目经理工作履历",false,{"key":20,"text":21,"correct":18},"C","项目经理持有的建造师执业资格证书",{"key":23,"text":24,"correct":14},"D","承包人为项目经理缴纳社会保险的有效证明",{"key":26,"text":27,"correct":18},"E","项目经理的专业技术职称证书","AD","本题考查的是施工企业项目经理的工作性质。项目经理应是承包人正式聘用的员工，承包人应向发包人提交项目经理与承包人之间的劳动合同，以及承包人为项目经理缴纳社会保险的有效证明。@jin",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]