[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-798-42":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":656},{"id":5,"name":6,"category":7,"favorite":8},798,"一建建设工程经济","建筑工程",0,42,50,2696,[13,34,46,58,70,82,94,112,126,138,150,162,174,189,204,216,231,243,255,270,282,297,309,321,335,347,359,371,382,396,405,416,428,440,452,464,478,493,507,519,531,543,555,567,579,591,603,615,630,644],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":30,"analysis":33},1139733,1,"单选题","（2020年真题）某建设工程施工过程中，由于发包人提供的材料没有及时到货,导致承包人自有的一台机械窝工四个台班。每台班折旧费500元。工作时每台班燃油动力费100元。另外，承包人租赁的一台机械窝工3个台班。台班租赁费为300元。工作时每台班燃油动力费80元。不考虑其他因素，则承包人可以索赔的费用为（ ）元。",[19,23,26,29],{"key":20,"text":21,"correct":22},"A","3540",false,{"key":24,"text":25,"correct":22},"B","3300",{"key":27,"text":28,"correct":22},"C","3140",{"key":30,"text":31,"correct":32},"D","2900",true,"",{"id":35,"libraryId":5,"type":15,"typeLabel":16,"stem":36,"options":37,"answer":20,"analysis":33},1139734,"（2020年真题）根据《建设工程施工合同（示范文本）》，质量保证金扣留的方式原则上采用（ ）。",[38,40,42,44],{"key":20,"text":39,"correct":32},"在支付工程进度款时逐次扣留",{"key":24,"text":41,"correct":22},"工程竣工结算时一次性扣留",{"key":27,"text":43,"correct":22},"按照里程碑扣留",{"key":30,"text":45,"correct":22},"签订合同后一次性扣留",{"id":47,"libraryId":5,"type":15,"typeLabel":16,"stem":48,"options":49,"answer":30,"analysis":33},1139735,"（2020年真题）《根据建设工程造价鉴定规范》下列现场签证争议鉴定的做法，正确的是（ ）。",[50,52,54,56],{"key":20,"text":51,"correct":22},"现场签证明确了人工、材料、机械台班数量及其价格的，按签证的数量和计日工的价格计算。",{"key":24,"text":53,"correct":22},"现场签证只有用工数量没有人工单价的，其人工单价比照鉴定项目相应工程人工单价计算",{"key":27,"text":55,"correct":22},"现场签证只有材料和机械台班用量没有价格的，其材料和台班价格按照鉴定项目相应工程的材料和台班单价适当上浮计算。",{"key":30,"text":57,"correct":32},"现场签证只有总价而无明细表述的，按总价款计算",{"id":59,"libraryId":5,"type":15,"typeLabel":16,"stem":60,"options":61,"answer":20,"analysis":33},1139736,"（2020年真题）根据《建设工程施工合同（示范文本）》关于工程保修期的说法，正确的是（ ）。",[62,64,66,68],{"key":20,"text":63,"correct":32},"发包人未经竣工验收擅自使用工程的保修期，自转移占有之日起算",{"key":24,"text":65,"correct":22},"各分部工程的保修期应该是相同的",{"key":27,"text":67,"correct":22},"工程保修期从工程完工之日起起算",{"key":30,"text":69,"correct":22},"工程保修期可以根据具体情况适当低于法定最低保修年限",{"id":71,"libraryId":5,"type":15,"typeLabel":16,"stem":72,"options":73,"answer":30,"analysis":33},1139737,"（2020年真题）根据《建设工程工程量清单计价规范》，关于单价合同计量的说法，正确的是（ ）。",[74,76,78,80],{"key":20,"text":75,"correct":22},"发包人可以在任何方便的时候计量，计量结果有效",{"key":24,"text":77,"correct":22},"承包人收到计量的通知后不跟人参加，则发包人的计量结果无效",{"key":27,"text":79,"correct":22},"承包人为保证施工质量超出施工图纸范围实施的工程量，应该予以计量",{"key":30,"text":81,"correct":32},"发包人应在计量前24小时通知到承包人，无论承包人是否参加，计量结果有效",{"id":83,"libraryId":5,"type":15,"typeLabel":16,"stem":84,"options":85,"answer":27,"analysis":33},1139738,"（2020年真题）根据《建设工程工程量清单计价规范》，关于暂列金额的说法，正确的是（ ）。",[86,88,90,92],{"key":20,"text":87,"correct":22},"暂列金额应根据招标工程量清单列出的内容和要求估算",{"key":24,"text":89,"correct":22},"暂列金额包括在签约合同价内，属承包人所有",{"key":27,"text":91,"correct":32},"已签约合同价中的暂列金额由发包人掌握使用",{"key":30,"text":93,"correct":22},"用于必然发生但暂时不能确定价格的材料、工程设备及专业工程的费用",{"id":95,"libraryId":5,"type":96,"typeLabel":97,"stem":98,"options":99,"answer":111,"analysis":33},1139739,2,"多选题","（2020年真题）根据《建设工程施工合同（示范文本）》对已缴纳履约保证金的承包人，其提交的竣工结算申请单的内容应包括（ ）。",[100,102,104,106,108],{"key":20,"text":101,"correct":32},"竣工结算合同价格",{"key":24,"text":103,"correct":22},"已经处理完的索赔资料",{"key":27,"text":105,"correct":32},"发包人已支付承包人的款项",{"key":30,"text":107,"correct":22},"应扣留的质保金",{"key":109,"text":110,"correct":32},"E","发包人应支付承包人的合同价款","ACE",{"id":113,"libraryId":5,"type":96,"typeLabel":97,"stem":114,"options":115,"answer":111,"analysis":33},1139740,"（2020年真题）根据《建设工程工程量清单计价规范》，因工程变更引起措施项目发生变化导致措施项目费调整，在措施项目拟实施方案得到发承包双方确认后，措施项目费调整的正确做法有（ ）。",[116,118,120,122,124],{"key":20,"text":117,"correct":32},"对采用总价计算的措施项目费，按实际发生变化的措施项目并考虑承包人报价浮动因素进行调整",{"key":24,"text":119,"correct":22},"除非措施项目费变动超过一定幅度，一般采用总价计算的措施项目费不能进行调整",{"key":27,"text":121,"correct":32},"采用单价计算的措施项目费，应按实际发生变化的措施项目和已标价工程量清单项目确定单价",{"key":30,"text":123,"correct":22},"安全文明施工费应按实际发生的措施项目计算，并考虑承包人报价浮动因素进行调整",{"key":109,"text":125,"correct":32},"安全文明施工费应按实际发生变化的措施项目调整，不得浮动",{"id":127,"libraryId":5,"type":15,"typeLabel":16,"stem":128,"options":129,"answer":27,"analysis":33},1139741,"根据《建筑安装工程费用项目组成》（建标[2003]206号），建筑安装工程造价中安全施工费的计算基础是（ ）。 (2012)",[130,132,134,136],{"key":20,"text":131,"correct":22},"人工费",{"key":24,"text":133,"correct":22},"材料费",{"key":27,"text":135,"correct":32},"直接工程费",{"key":30,"text":137,"correct":22},"直接费",{"id":139,"libraryId":5,"type":15,"typeLabel":16,"stem":140,"options":141,"answer":20,"analysis":33},1139742,"某采用工程量清单招标的工程，评标委员会发现某标书漏填了分部分项工程类清单中“地面找平”一项的综合单价和合价，则评标委员会的正确处理方式是（ ）。 (2012)",[142,144,146,148],{"key":20,"text":143,"correct":32},"视为该项费用已包含在工程量清单的其他单价和合价中",{"key":24,"text":145,"correct":22},"认定该标书为废标",{"key":27,"text":147,"correct":22},"要求投标人就此项进行单独报价，补充到原报价书中",{"key":30,"text":149,"correct":22},"由评标委员会认定一个合理价格补充到原报价书中",{"id":151,"libraryId":5,"type":15,"typeLabel":16,"stem":152,"options":153,"answer":30,"analysis":33},1139743,"根据《建设工程工程量清单计价规范》（GB50500-2013)．招标人委托工程造价咨询人编制的招标工程量清单．其封面应有招标人和（）盖章确认． (2013)",[154,156,158,160],{"key":20,"text":155,"correct":22},"编制清单的造价员",{"key":24,"text":157,"correct":22},"造价咨询人的造价工程师",{"key":27,"text":159,"correct":22},"工程造价咨询人的法人代表",{"key":30,"text":161,"correct":32},"工程造价咨询人",{"id":163,"libraryId":5,"type":15,"typeLabel":16,"stem":164,"options":165,"answer":30,"analysis":33},1139744,"关于国标工程投标报价的说法，错误的是( ) (2015)",[166,168,170,172],{"key":20,"text":167,"correct":22},"施工企业现场管理费应作为待摊费用分摊在各项综合单价中",{"key":24,"text":169,"correct":22},"现场试验设施费作为开办费应依赖招标文件决定是否单列",{"key":27,"text":171,"correct":22},"暂列金额由业主工程师决定是否全部或部分使用",{"key":30,"text":173,"correct":32},"人工费工日基价应按在工程所在国招募工人的平均日工资单价计算",{"id":175,"libraryId":5,"type":96,"typeLabel":97,"stem":176,"options":177,"answer":188,"analysis":33},1139745,"国际工程投标总报价组成中，应计入现场管理费的有( )。 (2014)",[178,180,182,184,186],{"key":20,"text":179,"correct":32},"差旅交通费",{"key":24,"text":181,"correct":22},"临时设施工程费",{"key":27,"text":183,"correct":22},"工程辅助费",{"key":30,"text":185,"correct":32},"劳动保护费",{"key":109,"text":187,"correct":32},"检验试验费","ADE",{"id":190,"libraryId":5,"type":96,"typeLabel":97,"stem":191,"options":192,"answer":203,"analysis":33},1139746,"关于国际工程投标报价中分项工程单价分析的说法，正确的有（）。2018真题 A、具有可靠定额标准的企业必须采用定额估价法进行单价分析计算",[193,195,197,199,201],{"key":20,"text":194,"correct":22},"匡算估价法适合于工程量较大并且所占费用比例较大的分项工程",{"key":24,"text":196,"correct":22},"机械搁置时间过长又无法在定额估价中给予恰当考虑时，采用作业估价法计",{"key":27,"text":198,"correct":32},"算机械费用更合适",{"key":30,"text":200,"correct":22},"采用作业估价法进行单价分析，估价师的实际经验直接决定估价的准确程度",{"key":109,"text":202,"correct":32},"为保证估价的正确与合理性，作业估价法的内容应包括制定施工计划和计算各项作业的资源费用等","CE",{"id":205,"libraryId":5,"type":15,"typeLabel":16,"stem":206,"options":207,"answer":20,"analysis":33},1139747,"国际工程投标报价时考虑工程项目的不同特点、类别、施工条件等情况采用低价策略的情形是（）。2018真题",[208,210,212,214],{"key":20,"text":209,"correct":32},"支付条件好的工程",{"key":24,"text":211,"correct":22},"专业要求高的技术密集型工程",{"key":27,"text":213,"correct":22},"竞争对手少的工程",{"key":30,"text":215,"correct":22},"工期要求急的工程",{"id":217,"libraryId":5,"type":96,"typeLabel":97,"stem":218,"options":219,"answer":230,"analysis":33},1139748,"投标人在国际工程投标的标前会议上的做法，正确的有（ ）。2017真题",[220,222,224,226,228],{"key":20,"text":221,"correct":32},"对工程内容范围不清的问题请业主作出说明",{"key":24,"text":223,"correct":32},"对容易产生歧义理解的合同条件，请业主给予解释",{"key":27,"text":225,"correct":22},"对投标文件中图纸与技术说明矛盾之处，提出己方的修改技术要求",{"key":30,"text":227,"correct":22},"提出对业主有利的设计方案修改建议",{"key":109,"text":229,"correct":22},"详细阐述己方施工方案的优势和竞争力","AB",{"id":232,"libraryId":5,"type":15,"typeLabel":16,"stem":233,"options":234,"answer":30,"analysis":33},1139749,"国际工程投标报价时，在工程所在国当地采购的材料设备，其预算价格应包括材料设备市场价、运输费和（）。2018真题",[235,237,239,241],{"key":20,"text":236,"correct":22},"港口费",{"key":24,"text":238,"correct":22},"样品费",{"key":27,"text":240,"correct":22},"银行手续费",{"key":30,"text":242,"correct":32},"采购保管损耗费",{"id":244,"libraryId":5,"type":15,"typeLabel":16,"stem":245,"options":246,"answer":30,"analysis":33},1139750,"国际工程项目招标中，如果业主规定了暂定工程量的分项内容和暂定总价款，且规定所有投标人都必须在总报价中加入这笔固定金额，则投标人对该暂定工程的报价策略是（ ). (2013)",[247,249,251,253],{"key":20,"text":248,"correct":22},"单价可适当降低",{"key":24,"text":250,"correct":22},"总价应适当降低",{"key":27,"text":252,"correct":22},"总价可适当提高",{"key":30,"text":254,"correct":32},"单价可适当提高",{"id":256,"libraryId":5,"type":96,"typeLabel":97,"stem":257,"options":258,"answer":269,"analysis":33},1139751,"影响国际工程投标报价决策的因素主要有（ ). (2013)",[259,261,263,265,267],{"key":20,"text":260,"correct":22},"评标人员组成",{"key":24,"text":262,"correct":32},"成本估算的准确性",{"key":27,"text":264,"correct":32},"竞争程度",{"key":30,"text":266,"correct":32},"市场条件",{"key":109,"text":268,"correct":32},"风险偏好","BCDE",{"id":271,"libraryId":5,"type":15,"typeLabel":16,"stem":272,"options":273,"answer":30,"analysis":33},1139752,"按照国际工程投标报价的程序，投标人在标前会议之前应该进行的工作是（ ）。 (2014)",[274,276,278,280],{"key":20,"text":275,"correct":22},"分包工程询价",{"key":24,"text":277,"correct":22},"人工、材料、机械基础单价计算",{"key":27,"text":279,"correct":22},"生产要素询价",{"key":30,"text":281,"correct":32},"进行各项调查研究",{"id":283,"libraryId":5,"type":96,"typeLabel":97,"stem":284,"options":285,"answer":296,"analysis":33},1139753,"关于国际工程招标中暂定金额的说法，正确的有（）（2016）",[286,288,290,292,294],{"key":20,"text":287,"correct":22},"承包商在投标报价时应将暂定金额在总报价之外单列",{"key":24,"text":289,"correct":32},"暂定金额的数量一般由业主在招标文件中明确",{"key":27,"text":291,"correct":32},"承包商在施工中无权做主使用暂定金额",{"key":30,"text":293,"correct":22},"暂定金额只能用于应对意外情况引起的损失",{"key":109,"text":295,"correct":32},"暂定金额应按照业主工程师的指令与决定，全部或部分使用","BCE",{"id":298,"libraryId":5,"type":15,"typeLabel":16,"stem":299,"options":300,"answer":20,"analysis":33},1139754,"某国际工程，业主方在招标文件中规定了200万元的暂定金额。则每一个承包商在投标报价时对该项暂定金额的正确处理方式是（） (2012)",[301,303,305,307],{"key":20,"text":302,"correct":32},"计入投标总报价，但承包商无权自主使用",{"key":24,"text":304,"correct":22},"计入投标总报价，并且承包商有权自主使用",{"key":27,"text":306,"correct":22},"不计入投标总价，在实际发生时由业主支付",{"key":30,"text":308,"correct":22},"不计入投标总价，由工程师决定是否使用",{"id":310,"libraryId":5,"type":15,"typeLabel":16,"stem":311,"options":312,"answer":27,"analysis":33},1139755,"关于国际工程投标报价中暂定金额的说法，错误的是( )。 (2014)",[313,315,317,319],{"key":20,"text":314,"correct":22},"暂定金额是业主在招标文件中明确规定了数额的一笔资金",{"key":24,"text":316,"correct":22},"承包商在投标报价时应将暂定金额计入工程总报价",{"key":27,"text":318,"correct":32},"暂定金额等同于暂估价",{"key":30,"text":320,"correct":22},"承包商无权做主使用暂定金额",{"id":322,"libraryId":5,"type":96,"typeLabel":97,"stem":323,"options":324,"answer":188,"analysis":33},1139756,"国际工程投标报价前，对估价人员算出的暂时标价进行动态分析时要考虑的因素有（ ）。 (2012)",[325,327,329,331,333],{"key":20,"text":326,"correct":32},"工期延误的影响",{"key":24,"text":328,"correct":22},"分项工程量变化的影响",{"key":27,"text":330,"correct":22},"地质勘察资料错误的影响",{"key":30,"text":332,"correct":32},"物价和工资上涨的影响",{"key":109,"text":334,"correct":32},"汇率，货款利率变化的影响",{"id":336,"libraryId":5,"type":15,"typeLabel":16,"stem":337,"options":338,"answer":20,"analysis":33},1139757,"国际工程投标报价时，对于预计施工现场发生的办公费，正确的做法是（）。 （2016）",[339,341,343,345],{"key":20,"text":340,"correct":32},"作为待摊费用摊入到工程量表的各计价分项价格中",{"key":24,"text":342,"correct":22},"作为待摊费单列并计入投标总标价",{"key":27,"text":344,"correct":22},"作为开办费单列并计入投标总报价",{"key":30,"text":346,"correct":22},"按照其费用性质分别计入相应分项工程的人工费、材料费或机票费",{"id":348,"libraryId":5,"type":15,"typeLabel":16,"stem":349,"options":350,"answer":27,"analysis":33},1139758,"关于工程量清单招标中计日工报价技巧的说法，正确的是（）。 (2013)",[351,353,355,357],{"key":20,"text":352,"correct":22},"单纯对计日工程报价应报低价",{"key":24,"text":354,"correct":22},"招标文件中有名义工程量的计日工程报高价",{"key":27,"text":356,"correct":32},"单纯对计日工程报价应报高价",{"key":30,"text":358,"correct":22},"招标文件中有名义工程量的计日工应报低价",{"id":360,"libraryId":5,"type":15,"typeLabel":16,"stem":361,"options":362,"answer":30,"analysis":33},1139759,"（2019年真题）企业会计核算中，施工企业行政管理部门使用的固定资产的维修费用属于（）",[363,365,367,369],{"key":20,"text":364,"correct":22},"财务费用",{"key":24,"text":366,"correct":22},"工程设备费用",{"key":27,"text":368,"correct":22},"施工机具使用费",{"key":30,"text":370,"correct":32},"管理费用",{"id":372,"libraryId":5,"type":15,"typeLabel":16,"stem":373,"options":374,"answer":27,"analysis":33},1139760,"（2019年真题）某国际工程，业主方在施工招标文件中规定了500万元的暂定金额，则承包商对该笔暂定金额的正确处理方式是（）",[375,377,379,381],{"key":20,"text":376,"correct":22},"不计入投标总价，发生时由工程师决定是否使用",{"key":24,"text":378,"correct":22},"计入投标总报价，并有权自主使用",{"key":27,"text":380,"correct":32},"计入投标总报价，但无权自主决定使用",{"key":30,"text":306,"correct":22},{"id":383,"libraryId":5,"type":96,"typeLabel":97,"stem":384,"options":385,"answer":111,"analysis":33},1139761,"（2019年真题）在国际工程报价中,投标人为了既不提高总报价,又能在结算中获得更理想的经济效益,运用不平衡报价法时,可以适当偏高报价的有( )。",[386,388,390,392,394],{"key":20,"text":387,"correct":32},"能早日结账收款的工程项目",{"key":24,"text":389,"correct":22},"预计不可能完全实施的早期工程项目",{"key":27,"text":391,"correct":32},"经核算预计今后工程量会增加较多的项目",{"key":30,"text":393,"correct":22},"预计工程量可能减少的后期工程项目",{"key":109,"text":395,"correct":32},"因设计图纸不明确可能导致工程量增加的项目",{"id":397,"libraryId":5,"type":15,"typeLabel":16,"stem":398,"options":399,"answer":30,"analysis":33},1139762,"（2020年真题）下列投标人在国标工程标前会议上的做法，正确的是（ ）。",[400,402,403,404],{"key":20,"text":401,"correct":22},"对招标文件中图纸与技术说明矛盾之处，提出己方的修改建议",{"key":24,"text":227,"correct":22},{"key":27,"text":229,"correct":22},{"key":30,"text":221,"correct":32},{"id":406,"libraryId":5,"type":15,"typeLabel":16,"stem":407,"options":408,"answer":24,"analysis":33},1139763,"（2020年真题）国际工程投标报价时，下列施工现场办公费的处理方式，正确的是（ ）。",[409,411,413,415],{"key":20,"text":410,"correct":22},"按照其费用性质分别计入相应分项工程的人工费、材料费或机具费",{"key":24,"text":412,"correct":32},"作为待摊费分摊到工程量清单的各个报价分项中",{"key":27,"text":414,"correct":22},"作为待摊费用单列并计入投标总报价",{"key":30,"text":344,"correct":22},{"id":417,"libraryId":5,"type":15,"typeLabel":16,"stem":418,"options":419,"answer":27,"analysis":33},1139764,"企业1~4 年每年年初向银行借款100 万元，借款年利率为10%，预计在6~9 年末等额本息偿还全部借款。则每年年末需要偿还的金额为（ ）万元。",[420,422,424,426],{"key":20,"text":421,"correct":22},"155.28",{"key":24,"text":423,"correct":22},"161.05",{"key":27,"text":425,"correct":32},"177.16",{"key":30,"text":427,"correct":22},"180.36",{"id":429,"libraryId":5,"type":15,"typeLabel":16,"stem":430,"options":431,"answer":30,"analysis":33},1139765,"某企业从金融机构借款100 万元，季度利率4%，按月复利计息，每季度付息一次，则该企业一年需向金融机构支付利息（ ）万元。",[432,434,436,438],{"key":20,"text":433,"correct":22},"4.06",{"key":24,"text":435,"correct":22},"12.68",{"key":27,"text":437,"correct":22},"16.24",{"key":30,"text":439,"correct":32},"16.21",{"id":441,"libraryId":5,"type":15,"typeLabel":16,"stem":442,"options":443,"answer":24,"analysis":33},1139766,"某银行借款利率12%，按季度复利计息，则该银行半年的有效利率为（ ）。",[444,446,448,450],{"key":20,"text":445,"correct":22},"6.15%",{"key":24,"text":447,"correct":32},"6.09%",{"key":27,"text":449,"correct":22},"6.28%",{"key":30,"text":451,"correct":22},"6.35%",{"id":453,"libraryId":5,"type":15,"typeLabel":16,"stem":454,"options":455,"answer":20,"analysis":33},1139767,"某企业第一年年初向A 银行借款500 万，借款利率为10%，预计在3~5 年末等额本息偿还贷款，则该企业每年偿还的贷款金额为（ ）万元。",[456,458,460,462],{"key":20,"text":457,"correct":32},"243.28",{"key":24,"text":459,"correct":22},"250.13",{"key":27,"text":461,"correct":22},"258.25",{"key":30,"text":463,"correct":22},"268.59",{"id":465,"libraryId":5,"type":96,"typeLabel":97,"stem":466,"options":467,"answer":188,"analysis":33},1139768,"下列选项中关于资金时间价值的说法，正确的是（ ）。",[468,470,472,474,476],{"key":20,"text":469,"correct":32},"在其他条件不变的情况下，资金使用时间越长，资金的时间价值越大",{"key":24,"text":471,"correct":22},"资金的周转速度越快，资金的时间价值越小",{"key":27,"text":473,"correct":22},"前期投入的越多，资金的正效益越大",{"key":30,"text":475,"correct":32},"任何资金的闲置，都是会损失资金的时间价值",{"key":109,"text":477,"correct":32},"在其他条件不变的情况下，资金数量越少，资金的时间价值越少",{"id":479,"libraryId":5,"type":96,"typeLabel":97,"stem":480,"options":481,"answer":492,"analysis":33},1139769,"下列关于现金流量图的绘制规则，说法正确的有（ ）。",[482,484,486,488,490],{"key":20,"text":483,"correct":22},"横轴表示时间轴，向右表示时间的延续，每一刻度表示一年",{"key":24,"text":485,"correct":22},"箭线长短需严格成比例绘制",{"key":27,"text":487,"correct":22},"横轴上的时点表示期初的时间",{"key":30,"text":489,"correct":32},"对投资人而言，横轴上方的箭线表示现金流入",{"key":109,"text":491,"correct":32},"正确绘制现金流量图需把握好现金流量的大小、方向、作用点","DE",{"id":494,"libraryId":5,"type":96,"typeLabel":97,"stem":495,"options":496,"answer":230,"analysis":33},1139770,"下列选项中，关于利率的说法，正确的是（ ）。",[497,499,501,503,505],{"key":20,"text":498,"correct":32},"利率的高低首先取决于社会平均利润率的高低",{"key":24,"text":500,"correct":32},"借出资本风险越大，利率越高",{"key":27,"text":502,"correct":22},"借出资本供过于求，利率上升；供小于求，利率下降",{"key":30,"text":504,"correct":22},"贷款资本期限越长，利率越小",{"key":109,"text":506,"correct":22},"利率和社会平均利润率是同比例变化的",{"id":508,"libraryId":5,"type":15,"typeLabel":16,"stem":509,"options":510,"answer":24,"analysis":33},1139771,"某常规技术方案当折现率为9%时，财务净现值为-180 万元，当折现率为7%时，财务净现值为30 万元，则关于财务内部收益率的说法，正确的有（ ）。",[511,513,515,517],{"key":20,"text":512,"correct":22},"小于7%",{"key":24,"text":514,"correct":32},"大于7%，小于8%",{"key":27,"text":516,"correct":22},"大于8%，小于9%",{"key":30,"text":518,"correct":22},"大于9%",{"id":520,"libraryId":5,"type":15,"typeLabel":16,"stem":521,"options":522,"answer":27,"analysis":33},1139772,"在进行财务分析的时候，对于非经营性方案，主要分析技术方案的（ ）。",[523,525,527,529],{"key":20,"text":524,"correct":22},"盈利能力",{"key":24,"text":526,"correct":22},"偿债能力",{"key":27,"text":528,"correct":32},"财务生存能力",{"key":30,"text":530,"correct":22},"营运能力",{"id":532,"libraryId":5,"type":15,"typeLabel":16,"stem":533,"options":534,"answer":20,"analysis":33},1139773,"某投资方案建设期为2 年，第1 年年初投资2000 万元，第2 年年初投资3000 万元，第三年年初开始运营，运营期为3 年，运营期每年年末净收益为3000 万元。若基准收益率为10%，则该投资方案的财务净现值为（ ）万元。",[535,537,539,541],{"key":20,"text":536,"correct":32},"1438.48",{"key":24,"text":538,"correct":22},"1628.56",{"key":27,"text":540,"correct":22},"2055.05",{"key":30,"text":542,"correct":22},"1498.62",{"id":544,"libraryId":5,"type":15,"typeLabel":16,"stem":545,"options":546,"answer":20,"analysis":33},1139774,"某企业拟新建一项目，有两个备选方案技术均可行。甲方案投资3000 万元。计算期15 年，财务净现值为300万元。乙方案投资5000 万元，计算期20 年，财务净现值为500 万元。则关于两方案比较的说法，正确的是（ ）。",[547,549,551,553],{"key":20,"text":548,"correct":32},"甲乙方案必须构造一个相同的分析期限才能比选",{"key":24,"text":550,"correct":22},"甲方案投资少于乙方案，净现值大于零，故甲方案较优",{"key":27,"text":552,"correct":22},"乙方案净现值大于甲方案，且都大于零，故乙方案较优",{"key":30,"text":554,"correct":22},"甲方案计算期短，说明甲方案的投资回收速度快于乙方案",{"id":556,"libraryId":5,"type":15,"typeLabel":16,"stem":557,"options":558,"answer":24,"analysis":33},1139775,"某技术方案的净现金流量如下表所示，则该技术方案的静态投资回收期为（ ）年。",[559,561,563,565],{"key":20,"text":560,"correct":22},"2.25",{"key":24,"text":562,"correct":32},"3.25",{"key":27,"text":564,"correct":22},"2.85",{"key":30,"text":566,"correct":22},"3.85",{"id":568,"libraryId":5,"type":15,"typeLabel":16,"stem":569,"options":570,"answer":27,"analysis":33},1139776,"经济效果评价的步骤包括：①熟悉技术方案的基本情况；②经济效果评价；③根据基础财务数据资料编制各基本财务报表；④收集、整理和计算有关技术经济基础数据资料与参数，关于经济效果评价的程序正确排序是（ ）。",[571,573,575,577],{"key":20,"text":572,"correct":22},"①②③④",{"key":24,"text":574,"correct":22},"④②①③",{"key":27,"text":576,"correct":32},"①④③②",{"key":30,"text":578,"correct":22},"④①③②",{"id":580,"libraryId":5,"type":15,"typeLabel":16,"stem":581,"options":582,"answer":24,"analysis":33},1139777,"某项目建设投资为4000 万元，建设期贷款利息为400 万元，全部流动资金为500 万元，项目投产期年息税前利润为800 万元，正常年份年息税前利润为1000 万元，则该项目的总投资收益率为（ ）。",[583,585,587,589],{"key":20,"text":584,"correct":22},"16.33%",{"key":24,"text":586,"correct":32},"20.41%",{"key":27,"text":588,"correct":22},"17.78%",{"key":30,"text":590,"correct":22},"22.22%",{"id":592,"libraryId":5,"type":15,"typeLabel":16,"stem":593,"options":594,"answer":27,"analysis":33},1139778,"某项目建设投资8000 万元，建设期贷款利息是300 万元，全部流动资金500 万元。项目投产期年息税前利润为1800 万元，运营期正常年份的年息税前利润为2200 万元，则该项目的总投资收益率为（ ）。",[595,597,599,601],{"key":20,"text":596,"correct":22},"20.45%",{"key":24,"text":598,"correct":22},"21.69%",{"key":27,"text":600,"correct":32},"25.00%",{"key":30,"text":602,"correct":22},"27.5%",{"id":604,"libraryId":5,"type":15,"typeLabel":16,"stem":605,"options":606,"answer":24,"analysis":33},1139779,"按照评价方法的性质不同，经济效果评价分为（ ）。",[607,609,611,613],{"key":20,"text":608,"correct":22},"静态分析和动态分析",{"key":24,"text":610,"correct":32},"定量分析和定性分析",{"key":27,"text":612,"correct":22},"融资前分析和融资后分析",{"key":30,"text":614,"correct":22},"事前分析和事后分析",{"id":616,"libraryId":5,"type":96,"typeLabel":97,"stem":617,"options":618,"answer":629,"analysis":33},1139780,"企业可以用来偿还投资借款的资金来源是（ ）。",[619,621,623,625,627],{"key":20,"text":620,"correct":32},"利润",{"key":24,"text":622,"correct":32},"折旧费",{"key":27,"text":624,"correct":22},"应付工资",{"key":30,"text":626,"correct":22},"应付税金",{"key":109,"text":628,"correct":32},"摊销费","ABE",{"id":631,"libraryId":5,"type":96,"typeLabel":97,"stem":632,"options":633,"answer":203,"analysis":33},1139781,"下列选项中属于盈利能力的动态指标是（ ）。",[634,636,638,640,642],{"key":20,"text":635,"correct":22},"投资收益率",{"key":24,"text":637,"correct":22},"投资回收期",{"key":27,"text":639,"correct":32},"财务净现值",{"key":30,"text":641,"correct":22},"利息备付率",{"key":109,"text":643,"correct":32},"财务内部收益率",{"id":645,"libraryId":5,"type":96,"typeLabel":97,"stem":646,"options":647,"answer":655,"analysis":33},1139782,"以下属于技术方案的盈利能力动态评价指标有（ ）。",[648,649,650,651,653],{"key":20,"text":643,"correct":32},{"key":24,"text":637,"correct":22},{"key":27,"text":639,"correct":32},{"key":30,"text":652,"correct":22},"流动比率",{"key":109,"text":654,"correct":22},"速动比率","AC",[657,660,663,666,669,672],{"id":15,"name":658,"category":7,"favorite":659},"领导干部任职前廉政法规知识测试题",92,{"id":661,"name":662,"category":7,"favorite":15},595,"建筑结构与设备",{"id":664,"name":665,"category":7,"favorite":15},715,"招标采购专业知识与法律法规",{"id":667,"name":668,"category":7,"favorite":15},848,"市政方向-通用基础",{"id":670,"name":671,"category":7,"favorite":8},534,"BIM工程师",{"id":673,"name":671,"category":7,"favorite":8},535]