[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-798-36":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":613},{"id":5,"name":6,"category":7,"favorite":8},798,"一建建设工程经济","建筑工程",0,36,50,2696,[13,34,46,57,69,81,93,104,116,128,141,153,165,177,189,201,213,225,240,252,266,278,289,301,313,323,336,350,365,375,383,395,407,416,428,440,452,464,479,488,500,511,519,530,545,553,565,577,589,601],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":24,"analysis":33},1139432,1,"单选题","某项目建设期2年，建设期内第1年贷款700万元，第2年贷款600万元，年内均衡发放，且只计息不还款，年利率为8%。则编制该项目的投资估算时，建设期利息总和为( )万元。 (2014)",[19,23,27,30],{"key":20,"text":21,"correct":22},"A","104.00",false,{"key":24,"text":25,"correct":26},"B","110.24",true,{"key":28,"text":29,"correct":22},"C","114.94",{"key":31,"text":32,"correct":22},"D","155.84","",{"id":35,"libraryId":5,"type":15,"typeLabel":16,"stem":36,"options":37,"answer":20,"analysis":33},1139433,"编制某工程项目投资估算时，项目建设期2年，第一年贷款800万元，第二年贷款600万元，贷款年利率10%，则该项日建设期利息总和为（）万元． (2013)",[38,40,42,44],{"key":20,"text":39,"correct":26},"154",{"key":24,"text":41,"correct":22},"114",{"key":28,"text":43,"correct":22},"140",{"key":31,"text":45,"correct":22},"144",{"id":47,"libraryId":5,"type":15,"typeLabel":16,"stem":48,"options":49,"answer":28,"analysis":33},1139434,"某建设工程项目的建设期为2年，第一年贷款600万元，第二年贷款800万元，贷款年利率10%，按年复利计息，则该项目建设期利息综合为（ ）万元。 (2012)",[50,52,53,55],{"key":20,"text":51,"correct":22},"103",{"key":24,"text":43,"correct":22},{"key":28,"text":54,"correct":26},"133",{"key":31,"text":56,"correct":22},"200",{"id":58,"libraryId":5,"type":15,"typeLabel":16,"stem":59,"options":60,"answer":24,"analysis":33},1139435,"根据《建筑安装工程费用项目组成》（建标【2013】44号文），建筑安装工程生产工人的高温作业临时津贴应计入（）。 （2016）",[61,63,65,67],{"key":20,"text":62,"correct":22},"劳动保护费",{"key":24,"text":64,"correct":26},"人工费",{"key":28,"text":66,"correct":22},"规费",{"key":31,"text":68,"correct":22},"企业管理费",{"id":70,"libraryId":5,"type":15,"typeLabel":16,"stem":71,"options":72,"answer":31,"analysis":33},1139436,"采用装运港船上交货价的进口设备，估算其购置费时，货价按照（ ）计算。 (2012)",[73,75,77,79],{"key":20,"text":74,"correct":22},"出厂价",{"key":24,"text":76,"correct":22},"到岸价",{"key":28,"text":78,"correct":22},"抵岸价",{"key":31,"text":80,"correct":26},"离岸价",{"id":82,"libraryId":5,"type":15,"typeLabel":16,"stem":83,"options":84,"answer":31,"analysis":33},1139437,"某项目拟从国外进口一套设备，重1000吨，装运港船上交货价300万美元，国际运费标准每吨360美元，海上运输保险费率0.266%。美元银行外汇牌价6.1元人民币。则该套设备国外运输保险费为（ ）万元。 (2015)",[85,87,89,91],{"key":20,"text":86,"correct":22},"4.868",{"key":24,"text":88,"correct":22},"4.881",{"key":28,"text":90,"correct":22},"5.452",{"key":31,"text":92,"correct":26},"5.467",{"id":94,"libraryId":5,"type":15,"typeLabel":16,"stem":95,"options":96,"answer":31,"analysis":33},1139438,"施工过程中，施工测量放线和复测工作发生的费用应计入( )。（2016）",[97,99,101,102],{"key":20,"text":98,"correct":22},"分部分项工程费",{"key":24,"text":100,"correct":22},"其他项目费",{"key":28,"text":68,"correct":22},{"key":31,"text":103,"correct":26},"措施项目费",{"id":105,"libraryId":5,"type":15,"typeLabel":16,"stem":106,"options":107,"answer":28,"analysis":33},1139439,"下列费用中，属于建筑安装工程费中措施项目费的是（ ）。 (2014)",[108,110,112,114],{"key":20,"text":109,"correct":22},"施工机具使用费",{"key":24,"text":111,"correct":22},"暂列金额",{"key":28,"text":113,"correct":26},"工程定位复测费",{"key":31,"text":115,"correct":22},"工程排污费",{"id":117,"libraryId":5,"type":15,"typeLabel":16,"stem":118,"options":119,"answer":28,"analysis":33},1139440,"施工现场设立的安全警示标志、现场围挡等所需的费用应计入()费用。 (2015)",[120,122,124,126],{"key":20,"text":121,"correct":22},"分部分项工程",{"key":24,"text":123,"correct":22},"规费项目",{"key":28,"text":125,"correct":26},"措施项目",{"key":31,"text":127,"correct":22},"其他项目",{"id":129,"libraryId":5,"type":130,"typeLabel":131,"stem":132,"options":133,"answer":140,"analysis":33},1139441,2,"多选题","下列建设工程投资费用中，属于工程建设其他费用中的场地准备及临时设施费有()。 (2015) A施工单位场地平整费B建设单位临时设施费 C环境影响评价费D遗留设施拆除清理费 E施工单位临时设施费",[134,135,136,137,138],{"key":20,"text":20,"correct":22},{"key":24,"text":24,"correct":26},{"key":28,"text":28,"correct":22},{"key":31,"text":31,"correct":26},{"key":139,"text":139,"correct":22},"E","BD",{"id":142,"libraryId":5,"type":15,"typeLabel":16,"stem":143,"options":144,"answer":31,"analysis":33},1139442,"为预测和分析建设项目存在的职业危险，危害因素种类及危害程度，并提出合理应对措施而产生的费用属于（） (2015)",[145,147,149,151],{"key":20,"text":146,"correct":22},"安全文明施工费",{"key":24,"text":148,"correct":22},"建设单位管理费",{"key":28,"text":150,"correct":22},"生产准备费",{"key":31,"text":152,"correct":26},"劳动安全卫生评价费",{"id":154,"libraryId":5,"type":15,"typeLabel":16,"stem":155,"options":156,"answer":31,"analysis":33},1139443,"某工程采购的一批钢材的出厂价为3980元\u002F吨，运费为50元\u002F吨，运输损耗率为0.5%，采购保管费为2%，则这批钢材的材料单价为（）元\u002F吨。（2016）",[157,159,161,163],{"key":20,"text":158,"correct":22},"4129.90",{"key":24,"text":160,"correct":22},"4079.90",{"key":28,"text":162,"correct":22},"4050.15",{"key":31,"text":164,"correct":26},"4131.15",{"id":166,"libraryId":5,"type":15,"typeLabel":16,"stem":167,"options":168,"answer":31,"analysis":33},1139444,"某施工材料采购原价为190元\u002F吨，运杂费为40元\u002F吨，运输损损耗率为1%，采购保管费率为3%，则该材料的单价为( )元\u002F吨。 (2014)",[169,171,173,175],{"key":20,"text":170,"correct":22},"234.28",{"key":24,"text":172,"correct":22},"237.66",{"key":28,"text":174,"correct":22},"239.20",{"key":31,"text":176,"correct":26},"239.27",{"id":178,"libraryId":5,"type":15,"typeLabel":16,"stem":179,"options":180,"answer":31,"analysis":33},1139445,"某施工机械预算价格为200万元，预计可使用10年，每年平均工作250个台班，预计净残值40万元。按工作量法计算折旧，则该机械台班折旧费为（ ）万元 (2015)",[181,183,185,187],{"key":20,"text":182,"correct":22},"0.8",{"key":24,"text":184,"correct":22},"0.64",{"key":28,"text":186,"correct":22},"0.06",{"key":31,"text":188,"correct":26},"0.064",{"id":190,"libraryId":5,"type":15,"typeLabel":16,"stem":191,"options":192,"answer":24,"analysis":33},1139446,"某施工机械购置费用为120万元，折旧年限为6年，年平均工作250个台班，预计净残值率为3%，按工作台班法提取折旧，该机械台班折旧费为（ ）元。 (2014)",[193,195,197,199],{"key":20,"text":194,"correct":22},"800",{"key":24,"text":196,"correct":26},"776",{"key":28,"text":198,"correct":22},"638",{"key":31,"text":200,"correct":22},"548",{"id":202,"libraryId":5,"type":15,"typeLabel":16,"stem":203,"options":204,"answer":28,"analysis":33},1139447,"某施工企业投标报价时确定企业管理费率以人工费为基础计算，据统计资料，该施工企业生产工人年平均管理费为1.2万元，年有效施工天数为240天，人工单价为300元\u002F天，人工费占分部分项工程费的比例为75%，则该企业的企业管理费费率应为（ ）。 (2015)",[205,207,209,211],{"key":20,"text":206,"correct":22},"12.15%",{"key":24,"text":208,"correct":22},"12.50%",{"key":28,"text":210,"correct":26},"16.67%",{"key":31,"text":212,"correct":22},"22.22%",{"id":214,"libraryId":5,"type":15,"typeLabel":16,"stem":215,"options":216,"answer":28,"analysis":33},1139448,"编制某企业改扩建项目的投资估算时，生产准备费的计算基数应为（）。（2016）",[217,219,221,223],{"key":20,"text":218,"correct":22},"新增建筑安装工程费用",{"key":24,"text":220,"correct":22},"原有设计定员",{"key":28,"text":222,"correct":26},"新增设计定员",{"key":31,"text":224,"correct":22},"全部设计定员",{"id":226,"libraryId":5,"type":130,"typeLabel":131,"stem":227,"options":228,"answer":239,"analysis":33},1139449,"下列费用中，应计入建设工程项目投资中“生产准备费”的有（ ） (2012)",[229,231,233,235,237],{"key":20,"text":230,"correct":26},"生产职工培训费",{"key":24,"text":232,"correct":22},"购买原材料、能源的费用",{"key":28,"text":234,"correct":22},"办公家具购置费",{"key":31,"text":236,"correct":22},"联合试运转费",{"key":139,"text":238,"correct":26},"提前进厂人员的工资、福利等费用","AE",{"id":241,"libraryId":5,"type":15,"typeLabel":16,"stem":242,"options":243,"answer":28,"analysis":33},1139450,"关于联合试运转费的说法，正确的是（ ）。 (2014)",[244,246,248,250],{"key":20,"text":245,"correct":22},"联合试运转费包括单机的调试费",{"key":24,"text":247,"correct":22},"联合试运转费包括单机安装后试运转中因施工质量原因发生的处理费用",{"key":28,"text":249,"correct":26},"联合试运转费应为联合试运转所发生的费用净支出",{"key":31,"text":251,"correct":22},"联合试运转支出主要是材料费，不包含人工费",{"id":253,"libraryId":5,"type":130,"typeLabel":131,"stem":254,"options":255,"answer":265,"analysis":33},1139451,"根据《建筑安装工程费用项目组成》（建标【2013】44号文），以定额人工为计费的基础规费有（）（2016）",[256,258,260,262,263],{"key":20,"text":257,"correct":26},"养老保险费",{"key":24,"text":259,"correct":26},"医疗保险费",{"key":28,"text":261,"correct":26},"工伤保险费",{"key":31,"text":115,"correct":22},{"key":139,"text":264,"correct":26},"住房公积金","ABCE",{"id":267,"libraryId":5,"type":15,"typeLabel":16,"stem":268,"options":269,"answer":28,"analysis":33},1139452,"某建设工程项目建筑安装工程费为2000万元，设备及工器具购置费为800万元，工程建设其他费用为300万元，基本预备费率为8%，该项目的基本预备费为（）万元。（2016）",[270,272,274,276],{"key":20,"text":271,"correct":22},"160",{"key":24,"text":273,"correct":22},"184",{"key":28,"text":275,"correct":26},"248",{"key":31,"text":277,"correct":22},"224",{"id":279,"libraryId":5,"type":15,"typeLabel":16,"stem":280,"options":281,"answer":28,"analysis":33},1139453,"某建设工程项目的设备及工器具购置费为2500万元，建筑安装工程费为2000万元，工程建设其他费为1500万元，基本预备费率为10%，则该项目的基本预备费为（ ）万元。 (2012)",[282,283,285,287],{"key":20,"text":56,"correct":22},{"key":24,"text":284,"correct":22},"400",{"key":28,"text":286,"correct":26},"600",{"key":31,"text":288,"correct":22},"450",{"id":290,"libraryId":5,"type":15,"typeLabel":16,"stem":291,"options":292,"answer":24,"analysis":33},1139454,"国家计量规范规定不宜计量的措施项目费的通用计算方法是（）（2016）",[293,295,297,299],{"key":20,"text":294,"correct":22},"∑（措施项目工程量*综合单价）",{"key":24,"text":296,"correct":26},"∑（计算基数*相应费率）",{"key":28,"text":298,"correct":22},"∑（直接工程费*相应费率）",{"key":31,"text":300,"correct":22},"∑（措施项目项数*综合单价）",{"id":302,"libraryId":5,"type":15,"typeLabel":16,"stem":303,"options":304,"answer":28,"analysis":33},1139455,"编制建设项目投资估算时，考虑项目在实施中可能会发生涉及变更增加工程量，投资计划中需要事先预留的费用是（ ） (2012)",[305,307,309,311],{"key":20,"text":306,"correct":22},"涨价预备费",{"key":24,"text":308,"correct":22},"铺底流动资金",{"key":28,"text":310,"correct":26},"基本预备费",{"key":31,"text":312,"correct":22},"工程建设其他费用",{"id":314,"libraryId":5,"type":15,"typeLabel":16,"stem":315,"options":316,"answer":20,"analysis":33},1139456,"根据现行《建筑安装工程费用项目组成》（建标【2013】44号），施工现场按规定缴纳的工程排污费应计入建筑安装工程（ ). (2013)",[317,318,320,322],{"key":20,"text":66,"correct":26},{"key":24,"text":319,"correct":22},"风险费用",{"key":28,"text":321,"correct":22},"措施费",{"key":31,"text":68,"correct":22},{"id":324,"libraryId":5,"type":130,"typeLabel":131,"stem":325,"options":326,"answer":335,"analysis":33},1139457,"根据《建筑安装工程项目组成》(建标[2013]44号)，下列费用中，属于规费的有( )。 (2014)",[327,329,331,333,334],{"key":20,"text":328,"correct":26},"社会保险费",{"key":24,"text":330,"correct":22},"安全施工费",{"key":28,"text":332,"correct":22},"环境保护费",{"key":31,"text":264,"correct":26},{"key":139,"text":62,"correct":22},"AD",{"id":337,"libraryId":5,"type":130,"typeLabel":131,"stem":338,"options":339,"answer":349,"analysis":33},1139458,"根据《建筑安装工程费用项目组成》（建标[2003]206号），建筑安装工程的规费包括（ ） (2012)",[340,341,343,345,347],{"key":20,"text":115,"correct":22},{"key":24,"text":342,"correct":26},"企业按规定标准为职工缴纳的养老保险费",{"key":28,"text":344,"correct":22},"企业为进行施工搭设临时设施的费用",{"key":31,"text":346,"correct":22},"施工机械停用期间的维护和保养费用",{"key":139,"text":348,"correct":26},"企业按规定标准为职工缴纳的住房公积金","BE",{"id":351,"libraryId":5,"type":130,"typeLabel":131,"stem":352,"options":353,"answer":364,"analysis":33},1139459,"下列工程建设其他费用中，属于建设单位管理费用的有( )。",[354,356,358,360,362],{"key":20,"text":355,"correct":26},"工程招标费",{"key":24,"text":357,"correct":22},"可行性研究费",{"key":28,"text":359,"correct":22},"工程监理费",{"key":31,"text":361,"correct":26},"竣工验收费",{"key":139,"text":363,"correct":26},"零星固定资产购置费","ADE",{"id":366,"libraryId":5,"type":130,"typeLabel":131,"stem":367,"options":368,"answer":140,"analysis":33},1139460,"根据《建设工程工程量清单计价规范》，应计入规费项目清单的费用有（）。2018真题",[369,370,371,372,373],{"key":20,"text":146,"correct":22},{"key":24,"text":115,"correct":26},{"key":28,"text":113,"correct":22},{"key":31,"text":261,"correct":26},{"key":139,"text":374,"correct":22},"增值税销项税额",{"id":376,"libraryId":5,"type":15,"typeLabel":16,"stem":377,"options":378,"answer":28,"analysis":33},1139461,"（2019年真题）根据《建设工程工程量清单计价规范》，施工企业为从事危险作业的建筑安装施工人员的的工伤保险费应计入建筑安装工程造价的（）。",[379,380,381,382],{"key":20,"text":64,"correct":22},{"key":24,"text":321,"correct":22},{"key":28,"text":66,"correct":26},{"key":31,"text":68,"correct":22},{"id":384,"libraryId":5,"type":15,"typeLabel":16,"stem":385,"options":386,"answer":24,"analysis":33},1139462,"（2019年真题）根据《建设工程工程量清单计价规范》，下列项目中，不得作为竞争性项目的是（）",[387,389,391,393],{"key":20,"text":388,"correct":22},"安全文明施工费、二次搬运费和税金",{"key":24,"text":390,"correct":26},"安全文明施工费、规费和税金",{"key":28,"text":392,"correct":22},"社会保险费，计日工和总承包服务费",{"key":31,"text":394,"correct":22},"暂列金额、规费和安全文明施工费",{"id":396,"libraryId":5,"type":15,"typeLabel":16,"stem":397,"options":398,"answer":24,"analysis":33},1139463,"（2019年真题）某建设项目的程费用为1500万元，工程建设其他费用为200万元，场地准备和临时设施费用的5%计算，预计项目完工后拆除工程产生的清理费用为20万元，拆除工程可收回材料作价5万元。则该项目的场地准备和临时设施费为( )万元。",[399,401,403,405],{"key":20,"text":400,"correct":22},"70",{"key":24,"text":402,"correct":26},"90",{"key":28,"text":404,"correct":22},"75",{"key":31,"text":406,"correct":22},"100",{"id":408,"libraryId":5,"type":15,"typeLabel":16,"stem":409,"options":410,"answer":20,"analysis":33},1139464,"（2019年真题）根据《建设工工程量清单计价规范》，总承包人为配合协调业主进行专业工程分包所需的用，在投与报价时应计入（）",[411,413,414,415],{"key":20,"text":412,"correct":26},"总承包服务费",{"key":24,"text":68,"correct":22},{"key":28,"text":103,"correct":22},{"key":31,"text":111,"correct":22},{"id":417,"libraryId":5,"type":15,"typeLabel":16,"stem":418,"options":419,"answer":31,"analysis":33},1139465,"（2019年真题）某建设项目分部分项工程的费用为20000万元(其中定额人工费占分部分项工程费的15%)，措施项目费为500万元，其他项目费为740万元。以上数据均不含增值税。规费为分部分项工程定额人工费的8%，增值税税率为9%，则该项目的招标控制价为()万元",[420,422,424,426],{"key":20,"text":421,"correct":22},"23151.60",{"key":24,"text":423,"correct":22},"24895.60",{"key":28,"text":425,"correct":22},"26421.60",{"key":31,"text":427,"correct":26},"23413.20",{"id":429,"libraryId":5,"type":15,"typeLabel":16,"stem":430,"options":431,"answer":24,"analysis":33},1139466,"（2019年真题）为保障施工机械正常运转所需的随机配备工具附具的摊销和维护费用，属于施工机具使用费中的()",[432,434,436,438],{"key":20,"text":433,"correct":22},"折旧费",{"key":24,"text":435,"correct":26},"经常修理费",{"key":28,"text":437,"correct":22},"施工仪器使用费",{"key":31,"text":439,"correct":22},"安拆费",{"id":441,"libraryId":5,"type":15,"typeLabel":16,"stem":442,"options":443,"answer":20,"analysis":33},1139467,"（2019年真题）下列费用中，属于工程建设其他费用中的联合试运转费的是()",[444,446,448,450],{"key":20,"text":445,"correct":26},"试运转过程中所需的专家指导费",{"key":24,"text":447,"correct":22},"试运转过程中因施工质量原因发生的处理费用",{"key":28,"text":449,"correct":22},"单台设备调试及试车费用",{"key":31,"text":451,"correct":22},"试运转过程中设备缺陷发生的处理费用",{"id":453,"libraryId":5,"type":15,"typeLabel":16,"stem":454,"options":455,"answer":31,"analysis":33},1139468,"（2019年真题）某施工机械预算价格为65万元，预计残值率为3%，折旧年限为5年（年限平均法折旧），每年工作250台班。折旧年限内预计每年大修理1次，每次费用为3万元。机械台班人工费为130元，台班燃料动力费为15元，台班车船税费为10元，不计台班安拆费及场外运费和经常修理费，则该机械台班单价为（）元。",[456,458,460,462],{"key":20,"text":457,"correct":22},"649.40",{"key":24,"text":459,"correct":22},"754.40",{"key":28,"text":461,"correct":22},"795.00",{"key":31,"text":463,"correct":26},"779.40",{"id":465,"libraryId":5,"type":130,"typeLabel":131,"stem":466,"options":467,"answer":478,"analysis":33},1139469,"（2019年真题）关于建筑安装工程人工费中日工资单价的说法，正确的有（）",[468,470,472,474,476],{"key":20,"text":469,"correct":22},"日工资单价是施工企业技术较熟练的生产工人在每工作日应得的工资总额",{"key":24,"text":471,"correct":26},"工程造价管理机构应参考项目实物工程量人工单价综合分析确定日工资单价",{"key":28,"text":473,"correct":26},"最低日工资单价不得低于工程所在地人力资源和社会保障部门发布的最低工资标准",{"key":31,"text":475,"correct":22},"企业投标报价时应自主确定日工资单价",{"key":139,"text":477,"correct":26},"工程计价定额中应根据项目技术要求和工种差别划分多种日工资单价","BCE",{"id":480,"libraryId":5,"type":15,"typeLabel":16,"stem":481,"options":482,"answer":20,"analysis":33},1139470,"（2020年真题）施工现场设立的安全警示标志，现场围挡等所需的费用属于（ ）费用",[483,484,485,487],{"key":20,"text":125,"correct":26},{"key":24,"text":121,"correct":22},{"key":28,"text":486,"correct":22},"零星项目",{"key":31,"text":127,"correct":22},{"id":489,"libraryId":5,"type":15,"typeLabel":16,"stem":490,"options":491,"answer":31,"analysis":33},1139471,"（2020年真题）从事建筑安装工程施工生产的工人，工伤期间的工资属于人工费中的（ ）。",[492,494,496,498],{"key":20,"text":493,"correct":22},"计时工资",{"key":24,"text":495,"correct":22},"津贴补贴",{"key":28,"text":497,"correct":22},"加班加点工资",{"key":31,"text":499,"correct":26},"特殊情况支付的工资",{"id":501,"libraryId":5,"type":15,"typeLabel":16,"stem":502,"options":503,"answer":24,"analysis":33},1139472,"（2020年真题）建设单位对设计方案进行评审所发生的费用应计入工程建设其他费用中的（ ）。",[504,506,508,510],{"key":20,"text":505,"correct":22},"专项评价费",{"key":24,"text":507,"correct":26},"建设管理费",{"key":28,"text":509,"correct":22},"勘察设计费",{"key":31,"text":359,"correct":22},{"id":512,"libraryId":5,"type":15,"typeLabel":16,"stem":513,"options":514,"answer":31,"analysis":33},1139473,"（2020年真题）建筑工人实名制管理费应计入（ ）",[515,516,517,518],{"key":20,"text":66,"correct":22},{"key":24,"text":100,"correct":22},{"key":28,"text":98,"correct":22},{"key":31,"text":103,"correct":26},{"id":520,"libraryId":5,"type":15,"typeLabel":16,"stem":521,"options":522,"answer":28,"analysis":33},1139474,"（2020年真题）下列费用项目中，属于施工企业管理费的是（ ）。",[523,525,527,528],{"key":20,"text":524,"correct":22},"生产工人津贴。",{"key":24,"text":526,"correct":22},"短期借款利息支出",{"key":28,"text":62,"correct":26},{"key":31,"text":529,"correct":22},"已完工程保护费",{"id":531,"libraryId":5,"type":130,"typeLabel":131,"stem":532,"options":533,"answer":544,"analysis":33},1139475,"（2020年真题）关于国产设备原价的说法，正确的有（ ）",[534,536,538,540,542],{"key":20,"text":535,"correct":22},"非标准国产设备原价中应包含运杂费",{"key":24,"text":537,"correct":26},"国产标准设备的原价一般是指出厂价",{"key":28,"text":539,"correct":26},"由设备成套公司供应的国产标准设备，原价为订货合同价",{"key":31,"text":541,"correct":26},"国产标准设备在计算原价时，一般按带有备件的出厂价计算",{"key":139,"text":543,"correct":26},"非标准国产设备原价的计算方法应简便，并使估算价格就近实际出厂价","BCDE",{"id":546,"libraryId":5,"type":15,"typeLabel":16,"stem":547,"options":548,"answer":20,"analysis":33},1139476,"（2020年真题）根据《建设工程工程量清单计价规范》，施工企业为建筑安装施工人员支付的失业保险费属于建筑安装工程费中的（ ）。",[549,550,551,552],{"key":20,"text":66,"correct":26},{"key":24,"text":64,"correct":22},{"key":28,"text":321,"correct":22},{"key":31,"text":68,"correct":22},{"id":554,"libraryId":5,"type":15,"typeLabel":16,"stem":555,"options":556,"answer":31,"analysis":33},1139477,"（2020年真题）将塔式起重机自停放地点运至施工现场的运输、拆卸、安装的费用属于（ ）。",[557,559,561,563],{"key":20,"text":558,"correct":22},"施工机械使用费",{"key":24,"text":560,"correct":22},"二次搬运费",{"key":28,"text":562,"correct":22},"固定资产使用费",{"key":31,"text":564,"correct":26},"大型机械进出场及安拆费",{"id":566,"libraryId":5,"type":15,"typeLabel":16,"stem":567,"options":568,"answer":28,"analysis":33},1139478,"编制人工定额时，基本工作结束后整理劳动工具时间应计入（）（2016）",[569,571,573,575],{"key":20,"text":570,"correct":22},"休息时间",{"key":24,"text":572,"correct":22},"不可避免的中断时间",{"key":28,"text":574,"correct":26},"有效工作时间",{"key":31,"text":576,"correct":22},"损失时间",{"id":578,"libraryId":5,"type":15,"typeLabel":16,"stem":579,"options":580,"answer":28,"analysis":33},1139479,"以建筑物或构筑物各个分部分项工程为对象编制的定额是（ ）。 (2012)",[581,583,585,587],{"key":20,"text":582,"correct":22},"施工定额",{"key":24,"text":584,"correct":22},"材料消耗定额",{"key":28,"text":586,"correct":26},"预算定额",{"key":31,"text":588,"correct":22},"概算定额",{"id":590,"libraryId":5,"type":15,"typeLabel":16,"stem":591,"options":592,"answer":20,"analysis":33},1139480,"编制人工定额时，工人定额工作时间中应予以合理考虑的情况是()。2018真题",[593,595,597,599],{"key":20,"text":594,"correct":26},"由于水源或电源终端引起的停工时间",{"key":24,"text":596,"correct":22},"由于工程技术人员和工人差错引起的工时损失",{"key":28,"text":598,"correct":22},"由于劳动组织不合理导致工作中断所占用的时间",{"key":31,"text":600,"correct":22},"由于材料供应不及时引起的停工时间",{"id":602,"libraryId":5,"type":15,"typeLabel":16,"stem":603,"options":604,"answer":20,"analysis":33},1139481,"关于周转性材料消耗及其定额的说法，正确的是（）。2018真题",[605,607,609,611],{"key":20,"text":606,"correct":26},"定额中周转材料消耗量应采用一次性使用量和摊销量两个指标表示",{"key":24,"text":608,"correct":22},"周转性材料消耗量只与周转性材料一次使用量和周转次数相关",{"key":28,"text":610,"correct":22},"施工企业成本核算投标报价应采用周转性材料的一次使用量指标",{"key":31,"text":612,"correct":22},"周转性材料的周转使用次数越多，则每周转使用一次材料的损耗越大",[614,617,620,623,626,629],{"id":15,"name":615,"category":7,"favorite":616},"领导干部任职前廉政法规知识测试题",92,{"id":618,"name":619,"category":7,"favorite":15},595,"建筑结构与设备",{"id":621,"name":622,"category":7,"favorite":15},715,"招标采购专业知识与法律法规",{"id":624,"name":625,"category":7,"favorite":15},848,"市政方向-通用基础",{"id":627,"name":628,"category":7,"favorite":8},534,"BIM工程师",{"id":630,"name":628,"category":7,"favorite":8},535]