[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140315":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1140315,798,1,"单选题","所有拟建项目在未作出最终决策之前，均应进行项目不确定性分析。下列不属于产生不确定性原因的是（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","所依据的基本数据不足",false,{"key":16,"text":17,"correct":14},"B","预测方法的局限",{"key":19,"text":20,"correct":14},"C","未来经济形势的变化",{"key":22,"text":23,"correct":24},"D","可用定量表示的影响因素",true,"2020\u002F2019版教材P32 产生不确定性因素的原因很多，一般情况下，产生不确定性的主要原因有以下几点：1.所依据的基本数据不足或者统计偏差。2.预测方法的局限，预测的假设不准确。3.未来经济形势的变化。4.技术进步。5.无法以定量来表示的定性因素的影响。6.其他外部影响因素，如政府政策的变化，新的法律、法规的颁布，国际政治经济形势的变化等，均会对技术方案的经济效果产生一定的甚至是难以预料的影响。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]