[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140314":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1140314,798,2,"多选题","对于建设项目来说，一般情况下，产生项目不确定性的主要原因有（ ）",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","基础数据统计偏差",true,{"key":16,"text":17,"correct":14},"B","未来市场需求结构的变化",{"key":19,"text":20,"correct":14},"C","预测方法的局限性",{"key":22,"text":23,"correct":24},"D","预测过程中出现的人为错误",false,{"key":26,"text":27,"correct":14},"E","通货膨胀","ABCE","2020\u002F2019版教材P32 产生不确定性因素的原因很多，一般情况下，产生不确定性的主要原因有以下几点：（1）所依据的基本数据不足或者统计偏差。（2）预测方法的局限，预测的假设不准确。（3）未来经济形势的变化。（4）技术进步。（5）无法以定量来表示的定性因素的影响。（6）其他外部影响因素，如政府政策的变化，新的法律、法规的颁布，国际政治经济形势的变化等。。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]