[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140260":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1140260,798,1,"单选题","下列关于投资者自行测定技术方案基准收益率的说法，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","基准收益率应不低于单位资金成本",false,{"key":16,"text":17,"correct":14},"B","基准收益率应不低于单位投资的机会成本",{"key":19,"text":20,"correct":21},"C","基准收益率应不低于min｛单位资金成本，单位投资机会成本｝",true,{"key":23,"text":24,"correct":14},"D","确定基准收益率必须考虑投资风险和通货膨胀因素","2020\u002F2019版教材P27 基准收益率应不低于max｛单位资金成本，单位投资机会成本｝，故C选项错误，D选项， 确定基准收益率的基础是资金成本和机会成本，而投资风险和通货膨胀则是必须考虑的影响因素。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]