[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140233":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1140233,798,1,"单选题","常规现金流量技术方案分析时，若采用的折现率提高，则（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","财务净现值减小，技术方案可行",false,{"key":16,"text":17,"correct":14},"B","财务净现值增加，技术方案可行",{"key":19,"text":20,"correct":21},"C","财务净现值减小，技术方案可能会不可行",true,{"key":23,"text":24,"correct":14},"D","财务净现值增加，技术方案不可行","2020\u002F2019版教材P25 考点:财务净现值与折现率的关系。对具有常规现金流量（即在计算期内，开始时有支出而后才有收益，且方案的净现金流量序列的符号只改变一次的现金流量）的技术方案，其财务净现值的大小与折现率的高低有直接的关系。随着折现率的逐渐增大，财务净现值由大变小，由正变负。折现率定得越高，技术方案被接受的可能性越小。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]