[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140220":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1140220,798,1,"单选题","某方案的净现值大于零，则该方案的内部收益率（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","一定小于行业基准收益率",false,{"key":16,"text":17,"correct":14},"B","一定大于贷款利率",{"key":19,"text":20,"correct":21},"C","一定大于行业基准收益率",true,{"key":23,"text":24,"correct":14},"D","一定小于社会平均利润率","2020\u002F2019版教材P25 财务净现值分析；财务内部收益率分析。内部收益率是指某方案净现值等于零时的折现率。而在计算某方案的净现值时采用的是设定折现率，采用设定折现率净现值大于零。折现率与净现值一定程度是成反比的。净现值小的折现率则大，故净现值为零的折现率即内部收益率大于设定折现率。由此可见，对独立常规技术方案应用FIRR评价与应用FNPV评价均可，其结论是一致的。个人理解，净现值大于0超额收益，需要超额收益，内部收益率同样必须大于行业基准收益率。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]