[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140196":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1140196,798,1,"单选题","项目投资回收期在一定程度上显示了资本的周转速度，下列表述正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","资本周转速度愈快，回收期愈长，风险愈小，项目抗风险能力愈强",false,{"key":16,"text":17,"correct":14},"B","资本周转速度愈快，回收期愈长，风险愈大，项目抗风险能力愈强",{"key":19,"text":20,"correct":14},"C","资本周转速度愈快，回收期愈短，风险愈大，项目抗风险能力愈弱",{"key":22,"text":23,"correct":24},"D","资本周转速度愈快，回收期愈短，风险愈小，项目抗风险能力愈强",true,"2020\u002F2019版教材P23 显然，资本周转速度愈快，静态投资回收期愈短，风险愈小，技术方案抗风险能力强。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]