[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140195":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1140195,798,1,"单选题","适合采用静态投资回收期评价的技术方案不包括( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","资金相当短缺的",false,{"key":16,"text":17,"correct":14},"B","技术上更新迅速的",{"key":19,"text":20,"correct":21},"C","资金充裕的",true,{"key":23,"text":24,"correct":14},"D","未来的情况很难预测而投资者又特别关心资金补偿的","2020\u002F2019版教材P23 四、在技术方案经济效果评价中，对于那些技术上更新迅速的技术方案，或资金相当短缺的技术方案，或未来的情况很难预测而投资者又特别关心资金补偿的技术方案，采用静态投资回收期评价特别有实用意义。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]