[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140192":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1140192,798,1,"单选题","将计算出的静态投资回收期Pt与所确定的基准投资回收期Pc进行比较，若技术方案可以考虑接受，则( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","Pt≤Pc",true,{"key":16,"text":17,"correct":18},"B","Pt>Pc",false,{"key":20,"text":21,"correct":18},"C","Pt≥0",{"key":23,"text":24,"correct":18},"D","Pt＜0","2020\u002F2019版教材P23 三、将计算出的静态投资回收期Pt与所确定的基准投资回收期Pc进行比较。若Pt=Pc，表明技术方案投资能在规定的时间内收回，则技术方案可以考虑接受；若PtPc，则技术方案是不可行的。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]