[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140188":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1140188,798,1,"单选题","下列关于建设项目投资风险分析的描述，正确的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投资回收期越长，项目抗风险能力越强",false,{"key":16,"text":17,"correct":18},"B","投资回收期越长，项目抗风险能力越弱",true,{"key":20,"text":21,"correct":14},"C","盈亏平衡点产量越高，项目抗风险能力越强",{"key":23,"text":24,"correct":14},"D","敏感性因素越不敏感，项目的风险越大","2020\u002F2019版教材P23 静态投资回收期指标容易理解，计算也比较简便，在一定程度上显示了资本的周转速度。显然，资本周转速度愈快，静态投资回收期愈短，风险愈小，技术方案抗风险能力强。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]