[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140186":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1140186,798,2,"多选题","下列不适合采用静态投资回收期指标评价的技术方案是( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","逐年收益相差较大的方案",true,{"key":16,"text":17,"correct":18},"B","资金相当短缺的方案",false,{"key":20,"text":21,"correct":14},"C","长期投资方案",{"key":23,"text":24,"correct":18},"D","技术上更新迅速的方案",{"key":26,"text":27,"correct":18},"E","未来情况很难预测而投资者又特别关心资金补偿的方案","AC","2020\u002F2019版教材P23 对于那些技术上更新迅速的技术方案，或资金相当短缺的技术方案，或未来的情况很难预测而投资者又特别关心资金补偿的技术方案，采用静态投资回收期评价特别有实用意义。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]