[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140183":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1140183,798,1,"单选题","静态投资回收期可借助技术方案投资现金流量表，根据净现金流量计算。当技术方案实施后各年的净收益均相同时，静态投资回收期=技术方案总投资／技术方案每年的净收益。但应用该式计算时应注意静态投资回收期的倒数( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不等于投资利润率",true,{"key":16,"text":17,"correct":18},"B","等于投资利润率",false,{"key":20,"text":21,"correct":18},"C","应根据累计现金流量求得",{"key":23,"text":24,"correct":18},"D","宜从技术方案投产后算起","2020\u002F2019版教材P22 由于技术方案的年净收益不等于年利润额，所以静态投资回收期不等于投资利润率的倒数。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]