[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140155":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1140155,798,1,"单选题","下列因素中，不能影响技术方案建设期长短的因素是（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","资金保障程度",false,{"key":16,"text":17,"correct":14},"B","实施条件",{"key":19,"text":20,"correct":21},"C","材料价格信息",true,{"key":23,"text":24,"correct":14},"D","管理组织","2020\u002F2019版教材P18 通常建设期应根据技术方案实施的内容、工程量大小、技术难易以及资金保障程度、实施条件和管理组织等多因素综合研究确定。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]