[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140153":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1140153,798,1,"单选题","下列关于建设项目财务评价指标的说法中，不正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","动态评价指标考虑了资金时间价值",false,{"key":16,"text":17,"correct":14},"B","静态评价指标没有考虑资金时间价值",{"key":19,"text":20,"correct":14},"C","动态评价指标反映了项目的盈利能力",{"key":22,"text":23,"correct":24},"D","静态评价指标的特点是考虑时间因素",true,"2020\u002F2019版教材P18 静态分析指标的最大特点是不考虑时间因素，计算简便。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]