[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140152":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1140152,798,1,"单选题","项目计算期指项目财务评价中为动态分析所设定的期限，包括（ ）．",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投产期和运营期",false,{"key":16,"text":17,"correct":18},"B","建设期和运营期",true,{"key":20,"text":21,"correct":14},"C","投产期和达产期",{"key":23,"text":24,"correct":14},"D","建设期和达产期","2020\u002F2019版教材P18 技术方案的计算期是指在经济效果评价中为进行动态分析所设定的期限，包括建设期和运营期。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]