[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140127":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1140127,798,1,"单选题","下述关于静态投资回收期的说法，错误的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","静态投资回收期考虑了资金的时间价值",true,{"key":16,"text":17,"correct":18},"B","静态投资回收期是在不考虑资金时间价值的条件下，以技术方案的净收益回收其全部投资所需要的时间",false,{"key":20,"text":21,"correct":18},"C","静态投资回收期不考虑资金的时间因素",{"key":23,"text":24,"correct":18},"D","静态投资回收期可以自技术方案投产年开始算起，但应予注明","2020\u002F2019版教材P21 技术方案静态投资回收期是在不考虑资金时间价值的条件下，以技术方案的净收益回收其总投资（包括建设投资和流动资金）所需要的时间，一般以年为单位。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]