[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1140002":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1140002,798,2,"多选题","下列各项属于国际工程投标报价过程中标价汇总组成项的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","分项工程合价",true,{"key":16,"text":17,"correct":18},"B","其他项目合价",false,{"key":20,"text":21,"correct":14},"C","暂定金额",{"key":23,"text":24,"correct":14},"D","分包工程总价",{"key":26,"text":27,"correct":18},"E","待摊费合价","ACD","本题考察的是国际工程投标报价的汇总。将工程量清单中所有分项工程的合价汇总，即可算出工程的总标价。总标价=分项工程合价+分包工程总价+暂定金额",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]