[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139996":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139996,798,2,"多选题","下列选项中既可以索赔工期，又可以索赔费用的是（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","异常恶劣的气候条件",false,{"key":16,"text":17,"correct":14},"B","发包人要求向承包人提前交付材料和工程设备",{"key":19,"text":20,"correct":14},"C","发包人要求承包人提前竣工",{"key":22,"text":23,"correct":24},"D","施工过程中发现文物、古迹",true,{"key":26,"text":27,"correct":24},"E","承包人遇到不利物质条件","DE","A 只能索赔工期；BC 只能索赔费用。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]