[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139995":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139995,798,2,"多选题","工程量的正确计量是发包人向承包人支付合同价款的前提和依据。下列选项中可以作为工程量计量依据的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","质量合格证书",true,{"key":16,"text":17,"correct":14},"B","《计量规范》",{"key":19,"text":20,"correct":21},"C","质量保修书",false,{"key":23,"text":24,"correct":14},"D","技术规范",{"key":26,"text":27,"correct":14},"E","设计图纸","ABDE","工程量计量依据的有质量合格证书、《计量规范》和技术规范、设计图纸。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]