[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139994":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139994,798,2,"多选题","根据《建设工程施工合同（示范文本）》(GF-2017-0201)，合同履行期间,市场价格波动引起的人工、材料、工程设备、机械台班价格波动影响合同价格时，计算调整合同价款的方法可以是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","价格指数修正法",false,{"key":16,"text":17,"correct":18},"B","造价信息进行价格调整法",true,{"key":20,"text":21,"correct":18},"C","价格指数调整法",{"key":23,"text":24,"correct":14},"D","直接替代法",{"key":26,"text":27,"correct":18},"E","专用合同条款约定的其他方式","BCE","市场价格波动引起的调整包括：（1）使用价格指数进行价格调整（2）采用造价信息进行价格调整（3）专用合同条款约定的其他方式。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]