[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139992":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139992,798,2,"多选题","根据《建设工程施工合同（建设工程施工合同（示范文本）》（GF-2017-0201），因不可抗力事件导致的损害及其费用增加，应由发包人承担的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程本身的损害",true,{"key":16,"text":17,"correct":18},"B","承包人的施工机械损坏",false,{"key":20,"text":21,"correct":14},"C","发包方现场办公室的损坏",{"key":23,"text":24,"correct":14},"D","工程所需的修复费用",{"key":26,"text":27,"correct":14},"E","因工程原因造成的第三方人员伤亡","ACDE","本题考查的是不可抗力的责任划分。不可抗力导致的人员伤亡、财产损失、费用增加和(或)工期延误等后果，由合同当事人按以下原则承担：(1)永久工程、已运至施工现场的材料和工程设备的损坏，以及因工程损坏造成的第三方人员伤亡和财产损失由发包人承担；(2)承包人施工设备的损坏由承包人承担；(3)发包人和承包人承担各自人员伤亡和财产的损失；(4)因不可抗力影响承包人履行合同约定的义务.已经引起或将引起工期延误的，应当顺延工期，由此导致承包人停工的费用损失由发包人和承包人合理分担，停工期间必须支付的工人工资由发包人承担；(5)因不可抗力引起或将引起工期延误。发包人要求赶工的，由此增加的赶工费用由发包人承担；(6)承包人在停工期间按照发包人要求照管、清理和修复工程的费用由发包人承担。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]