[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139991":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139991,798,2,"多选题","根据《建设工程施工合同（示范文本）》(GF-2017-0201)，关于提出索赔期限的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","若承包人按约定接受竣工付款证书后，应被视为无权再提出任何索赔要求",false,{"key":16,"text":17,"correct":18},"B","若承包人按约定接受竣工付款证书后，应被视为无权再提出工程接受证书颁发前发生的索赔",true,{"key":20,"text":21,"correct":18},"C","若承包人按约定提交最终结清申请单，只限于提出工程接受证书后发生的索赔",{"key":23,"text":24,"correct":18},"D","承包人提出索赔的期限应自接受最终结清证书为止",{"key":26,"text":27,"correct":14},"E","承包人提出索赔的期限是竣工结算后28 天内","BCD","承包人按“竣工结算审核”条款约定接收竣工付款证书后，应被视为已无权再提出在工程接收证书颁发前所发生的任何索赔。承包人按“最终结清”条款提交的最终结清申请单中，只限于提出工程接收证书颁发后发生的索赔。提出索赔的期限自接受最终结清证书时终止。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]