[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139990":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139990,798,2,"多选题","根据《建设工程工程量清单计价规范》GB 50500-2013,关于单价合同工程计量的说法，正确的有（ ）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","承包人认为发包人核实后的计量结果有误，应及时提出书面报告",true,{"key":16,"text":17,"correct":18},"B","承包人应于每月20 日向监理人报送上月20 日至19 日已完成的工程量报告",false,{"key":20,"text":21,"correct":18},"C","工程量按承包人在履行合同义务过程中实际施工的工程量确定",{"key":23,"text":24,"correct":14},"D","对于承包人原因造成超出施工图纸范围施工的工程量，不予计量",{"key":26,"text":27,"correct":14},"E","对工程变更引起工程量的增减变化,应据实调整,正确计量","ADE","B 承包人应于每月25 日向监理人报送上月20 日至当月19 日完成的工程量报告，并附具进度付款申请单、已完成工程量报表和有关资料。C 工程量必须以承包人完成合同工程应予计量的工程量确定。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]