[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139987":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1139987,798,1,"单选题","下列选项中，关于设备费的索赔，说法不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工作内容增加引起的索赔，设备费的标准按机械台班费计算",false,{"key":16,"text":17,"correct":18},"B","窝工引起的索赔，按台班折旧费计算",true,{"key":20,"text":21,"correct":14},"C","发包人未按约定时间付款的，应按约定利率支付迟延付款的利息",{"key":23,"text":24,"correct":14},"D","工作变更引起的索赔，承包人可按原报价单中的利润百分率计算利润","当工作内容增加引起设备费索赔时，设备费的标准按照机械台班费计算。因窝工引起的设备费索赔，当施工机械属于施工企业自有时，按照机械折旧费计算索赔费用；当施工机械是施工企业从外部租赁时，索赔费用的标准按照设备租赁费计算。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]