[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139986":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1139986,798,1,"单选题","根据《建设工程工程量清单计价规范》(GB50500-2013)，因不可抗力事件导致的损害及其费用增加，应由承包人承担的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程本身的损害",false,{"key":16,"text":17,"correct":14},"B","发包人现场的人员伤亡",{"key":19,"text":20,"correct":14},"C","已运至现场的水泥",{"key":22,"text":23,"correct":24},"D","承包人施工设备的损坏",true,"根据《建设工程工程量清单计价规范》(GB50500-2013)，因不可抗力事件导致的损害及其费用增加，承包人只承担自己的人员伤亡和施工机械设备损坏及停工损失。承包人在停工期间按照发包人要求照管、清理和修复工程的费用由发包人承担。D 选项承人施工设备的损坏由承包人承担",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]