[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139985":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1139985,798,1,"单选题","某项目实际工程量相比清单工程量的减少了16%，招标控制价的综合单价为400 元，投标报价的综合单价为300 元，该工程投标报价下浮率为6%，则该工程的综合单价应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不做调整",false,{"key":16,"text":17,"correct":18},"B","调整为319.6 元",true,{"key":20,"text":21,"correct":14},"C","调整为239.7 元",{"key":23,"text":24,"correct":14},"D","调整为460 元","400×（1-15%）×（1-6%）=319.6 元；319.6>300，所以调整为319.6元。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]