[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139984":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139984,798,1,"单选题","根据《建设工程施工合同（示范文本）》(GF-2017-0201)，除专用合同条款另有约定的外，因工程量变化引起的综合单价调整应支付的时间是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","变更事项完成后，立即支付",false,{"key":16,"text":17,"correct":14},"B","计入最终的结算款中支付",{"key":19,"text":20,"correct":21},"C","计入最近的一期进度款中支付",true,{"key":23,"text":24,"correct":14},"D","与最终索赔款项一起支付","因变更引起的价格调整应计入最近一期的进度款中支付。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]