[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139982":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139982,798,1,"单选题","某工程项目预付款120 万元，合同约定：每月进度款按结算价的80%支付；每月支付安全文明施工费20 万元；预付款从开工的第4 个月起分3 个月等额扣回，开工前6 个月结算价如下表，则第4 个月应支付的款项为（ ）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","212",false,{"key":16,"text":17,"correct":14},"B","192",{"key":19,"text":20,"correct":21},"C","172",true,{"key":23,"text":24,"correct":14},"D","152","240×80%+20-120\u002F3=192-20=172 万元",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]