[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139979":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1139979,798,1,"单选题","增加工作内容产生的人工费应按（ ）计算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","窝工费",false,{"key":16,"text":17,"correct":18},"B","计日工",true,{"key":20,"text":21,"correct":14},"C","补贴费",{"key":23,"text":24,"correct":14},"D","加班费","索赔的人工费包括：增加工作内容的人工费、停工损失费和工作效率降低的损失费等累计，其中增加工作内容的人工费应按照计日工费计算，而停工损失费和工作效率降低的损失费按窝工费计算，窝工费的标准双方应在合同中约定。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]