[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139978":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139978,798,1,"单选题","根据《建设工程施工合同（示范文本）》，发生工程变更的，承包人应在收到变更指示后（ ）内，向监理人提交变更估价申请。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","10",{"key":19,"text":20,"correct":21},"C","14",true,{"key":23,"text":24,"correct":14},"D","15","本题考查工程变更估价的程序。承包人应在收到变更指示后14天内，向监理人提交变更估价申请。 监理人应在收到承包人提交的变更估价申请后7天内审查完毕并报送发包人，监理人对变更估价申请有异议，通知承包人修改后重新提交。发包人应在承包人提交变更估价申请后14天内审批完毕。发包人逾期未完成审批或未提出异议的，视为认可承包人提交的变更估价申请。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]