[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139974":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139974,798,1,"单选题","下列不属于导致工程量清单缺项原因的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设计变更",false,{"key":16,"text":17,"correct":14},"B","工程量清单编制错误",{"key":19,"text":20,"correct":21},"C","施工方案调整",true,{"key":23,"text":24,"correct":14},"D","施工条件改变","本题考查的是导致工程量清单缺项的原因。施工过程中，工程量清单项目的增减变化必然带来合同价款的增减变化。而导致工程量清单缺项的原因，一是设计变更；二是施工条件改变.；三是工程量清单编制错误。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]