[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139973":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1139973,798,1,"单选题","某工程在施工过程中,因不可抗力造成损失，造成永久工程损失26 万元、承包人受伤人员医药费4.5 万元、承包人施工机具损坏损失12 万元、停工期间按照发包人要求清理和修复工程的费用3.5 万元。承包人及时向项目监理机构提出了索赔申请，承包人可以获得的索赔金额为（ ）万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","46",false,{"key":16,"text":17,"correct":14},"B","42.5",{"key":19,"text":20,"correct":14},"C","33",{"key":22,"text":23,"correct":24},"D","29.5",true,"本题考查的是不可抗力的责任划分。不可抗力导致的人员伤亡、财产损失、费用增加和(或)工期延误等后果，由合同当事人按以下原则承担：(1)永久工程、已运至施工现场的材料和工程设备的损坏，以及因工程损坏造成的第三方人员伤亡和财产损失由发包人承担；(2)承包人施工设备的损坏由承包人承担；(3)发包人和承包人承担各自人员伤亡和财产的损失；(4)因不可抗力影响承包人履行合同约定的义务，已经引起或将引起工期延误的，应当顺延工期，由此导致承包人停工的费用损失由发包人和承包人合理分担，停工期间必须支付的工人工资由发包人承担；(5)因不可抗力引起或将引起工期延误。发包人要求赶工的，由此增加的赶工费用由发包人承担；(6)承包人在停工期间按照发包人要求照管、清理和修复工程的费用由发包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]