[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139970":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1139970,798,1,"单选题","根据《建设工程施工合同（示范文本）》(GF-2017-0201)，监理人未按合同约定时间对承包人提交的已完工程量报告进行核实的，则应采取的做法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","要求承包人重新提交已完工程量报告",false,{"key":16,"text":17,"correct":18},"B","将计量报告中所列的工程量视为承包人实际完成的工程量",true,{"key":20,"text":21,"correct":14},"C","要求承包人提交证明已完工程量属实的证明材料",{"key":23,"text":24,"correct":14},"D","将计量报告中所列的工程量的80%视为承包人实际完成的工程量","监理人未在收到承包人提交的工程量报表后的7 天内完成审核的，承包人报送的工程量报告中的工程量视为承包人实际完成的工程量，据此计算工程价款。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]