[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139966":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139966,798,1,"单选题","施工过程中发生的计日工没有相应单价的，应如何处理（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发承包双方按合理的成本加利润重新商定综合单价",true,{"key":16,"text":17,"correct":18},"B","计日工发生时承包人提出的综合单价",false,{"key":20,"text":21,"correct":18},"C","计日工发生当月市场人工工资单价",{"key":23,"text":24,"correct":18},"D","计日工发生当月造价管理部门发布的人工指导价","本题考查的是计日工。任一计日工项目实施结束后，承包人应按照确认的计日工现场签证报告核实该类项目的工程数量，并应根据核实的工程数量和承包人已标价工程量清单中的计日工单价计算，提出应付价款；已标价工程量清单中没有该类计日工单价的，由发承包双方按合理的成本加利润商定计日工单价计算。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]