[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139964":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1139964,798,1,"单选题","根据《建设工程施工合同（示范文本）》(GF-2017-0201)，承包人应在收到变更指令后（ ）内向监理人提交变更估价申请。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7 天",false,{"key":16,"text":17,"correct":18},"B","14 天",true,{"key":20,"text":21,"correct":14},"C","21 天",{"key":23,"text":24,"correct":14},"D","28 天","承包人应在收到变更指示后14 天内，向监理人提交变更估价申请。监理人应在收到承包人提交的变更估价申请后7 天内审查完毕并报送发包人，监理人对变更估价申请有异议，通知承包人修改后重新提交。发包人应在承包人提交变更估价申请后14 天内审批完毕。发包人逾期未完成审批或未提出异议的，视为认可承包人提交的变更估价申请。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]