[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139962":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1139962,798,1,"单选题","根据《建设工程施工合同（示范文本）》(GF-2017-0201)，工程预付款支付应按照专用合同的约定执行，但最迟支付的时间是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","签订施工合同后30 天内",false,{"key":16,"text":17,"correct":18},"B","开工通知载明的开工日期7 天前",true,{"key":20,"text":21,"correct":14},"C","收到中标通知书并确认后30 天内",{"key":23,"text":24,"correct":14},"D","实际开工前14 天","按《建设工程施工合同（示范文本）》（GF-2017-0201），预付款的支付按照专用合同条款约定执行，但至迟应在开工通知载明的开工日期7 天前支付。预付款应当用于材料、工程设备、施工设备的采购及修建临时工程、组织施工队伍进场等。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]