[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139958":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139958,798,2,"多选题","下列选项中，属于其他项目费的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","暂列金额",true,{"key":16,"text":17,"correct":14},"B","总承包服务费",{"key":19,"text":20,"correct":21},"C","夜间施工增加费",false,{"key":23,"text":24,"correct":21},"D","工程定位复测费",{"key":26,"text":27,"correct":14},"E","计日工","ABE","其他项目费：暂列金额、暂估价、计日工、总承包服务费。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]