[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139957":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139957,798,2,"多选题","在计算措施项目费时，可以采用综合单价法的是（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","混凝土模板工程",true,{"key":16,"text":17,"correct":14},"B","脚手架工程",{"key":19,"text":20,"correct":14},"C","垂直运输工程",{"key":22,"text":23,"correct":24},"D","二次搬运费",false,{"key":26,"text":27,"correct":24},"E","室内空气污染测试费","ABC","措施项目费的计算方法： （1）综合单价法：混凝土模板、脚手架、垂直运输 （2）参数法计价：安全文明施工费、夜间施工增加费、二次搬运费、冬雨季施工增加费、已完工程及设备保护费。 （3）分包法计价： 能独立分包的项目，如室内空气污染测试。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]