[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139947":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1139947,798,1,"单选题","根据《建设工程工程量清单计价规范》（GB50500-2013），下列计价公式不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分部分项工程费=?分部分项工程量′分部分项工程综合单价",false,{"key":16,"text":17,"correct":18},"B","措施项目费=?措施项目工程量′措施项目综合单价",true,{"key":20,"text":21,"correct":14},"C","单位工程报价=分部分项工程费+措施项目费+其他项目费+规费+税金",{"key":23,"text":24,"correct":14},"D","单项工程报价= ?单位工程报价","本题考查的是工程造价计算及汇总的方法。利用综合单价法计价需分项计算清单项目，再汇总得到工程总造价。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]