[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139945":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1139945,798,1,"单选题","发包人应在收到承包人的签证报告（ ）内给予确认或提出修改意见，否则视为该签证报告已经认可。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","24 小时",false,{"key":16,"text":17,"correct":18},"B","48 小时",true,{"key":20,"text":21,"correct":14},"C","3 天",{"key":23,"text":24,"correct":14},"D","7 天","本题考查的是现场签证的程序。发包人应在收到承包人的签证报告48小时内给予确认或提出修改意见，否则视为该签证报告已经认可。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]